All asphalt works in Pulteney Street, Taree have been completed and line marking was to be completed on Thursday, August 9.
Subscribe now for unlimited access.
$0/
(min cost $0)
or signup to continue reading
The southbound lane will be open to traffic/parking from tomorrow Friday, August 10. The northbound lane will remain closed for driveway/footpath works.
All works are estimated to be finished by next Friday, August 17
Work started on the split-level section of Pulteney Street, Taree in April.
The section targeted for its failed pavement runs from Albert Street to Wynter Street, with contractors undertaking a full reconstruction of both lanes as well as driveway replacements, footpaths in front of businesses, stairs and median islands and roadside drainage improvements.
Shortly after the start of the project stormwater caused havoc for contractors and it was neccesary to revise the schedule of works, altering access conditions for local businesses and residents in the work zone.
.